Project Name:
Greif Paperboard Cardboard Plant
Location:
Mobile, Alabama
Start Date:
2020
Project Type:
- Industrial
End Date:
2022
Services Used:
- Demolition
- Environmental Remediation & Site Restoration
Project Description
This project consisted of the demolition and site closure of the former cardboard plant. This included the closure of 2 ponds and removed, transported and disposed of 10,000 cubic yards of waste material, as well as backfilling and grading the prior pond area with 5,000 CY of imported soil. SWPPP was installed and maintained throughout the project.